Nationally significant infrastructure projects: advice on the preparation and submission of application documents The Construction Information Service
We connect trusted knowledge to customers’ workflows – mitigating risk, increasing efficiency and accelerating innovation For more than 60 years, leading R&D and engineering-intensive organizations have relied on us to achieve on-time, on-budget delivery of complex projects and new products. If you are an applicant and have any questions about the impact of these changes on the service you are receiving, please contact your assigned case manager or You can sign up for alerts when changes are made via the GOV UK pages. We are undertaking a further detailed review of our NSIP advice page collection from this summer to fully align our published advice with the amended legal and guidance framework. These initial updates include, amongst other things, the removal of references to the obsolete statutory requirement for applicants to carry out pre-application consultation. At the Planning Inspectorate we publish advice pages about running the infrastructure planning process which are drawn from experience and good practice.
If a printed copy of the application is needed, the paper application should be organised in the same way as the electronic version. To improve accessibility of the documents published on our website all documents should be numbered methodically. However, the plans should be logically referenced and clearly signposted. If a prescribed document is included within another document, applicants should make it clear where this document can be found including the relevant reference, page, paragraph, and appendix numbers.
As a result of the changes to the process introduced on 24 July 2026, some features of the pre-application service offer set out in the 2024 Pre-application Prospectus are obsolete. All future updates will be published on our GOV.UK pages. Government has published guidance which explains and supports the changes on its National Infrastructure Planning Guidance Portal. These amendments affect the process of applying for, and making representations about, applications for nationally significant infrastructure projects (NSIPs). Following the submission of the application, the Planning Inspectorate will publish the application documents on the Find a National Infrastructure Project website as soon as practicable.
Where sequenced drawings and sections are used, a key plan and the cited document sequence or section notation should be provided. Plans and drawings should comply with the requirements set out in regulation 5 (and where applicable regulation 6) of the APFP regulations. Images without the explicit consent of such persons will not be considered or published as part of an application. Photographs that can identify a person should not be used, unless that person has consented to their image being published.
If the applicant fails to pay the final payment within the specified time, this could have impacts on the application process. The fee to accompany the application must be paid when the NSIP application is submitted. Any outstanding pre-application fees charged by the Planning Inspectorate will need to be paid by the applicant before submission of their NSIP application. From October 2024, the Planning Inspectorate has been charging fees for its advice and services provided to applicants during the pre-application stage. For NSIPs in Wales, applicants should provide appropriate application documents in English and Welsh.
The Examining Authority may ask for printed copies of some, or all, of the application documents or information before or during examination. Applicants should not submit video or audio information unless agreed beforehand with the Planning Inspectorate. The Planning Inspectorate’s case team can provide further information on this matter on request. Professional parties are responsible for ensuring their submissions are accurate and lawful.
Applicants should discuss with the Planning Inspectorate about how their application and supporting information should be prepared and submitted. The Planning Inspectorate processes planning and enforcement appeals and holding examinations into regional spatial strategies and local development plans. The process guide on the Find a National Infrastructure Project website will also be updated during this week to reflect the changes.
Applicants need to comply with Section 56(6) of the Planning Act and regulation 8 of the APFP regulations and provide the application and supporting documents in a format that can be published on the ‘Find a National Infrastructure Project website’. To fulfil this request, applicants should request an editable version of the latest published advice log from the Planning Inspectorate prior to submission. The prescribed application form will be populated during the submission process and automatically added to the submission documents. Government guidance on the pre-application stage published on the National Infrastructure Planning Guidance Portal provides further information on the content of applications. The ability to change a submitted application is limited and we cannot accept new information during the acceptance stage.
This may include explaining why in the applicant’s view the s51 advice is not relevant to the circumstances of the application, or why the matter concerned is one that should be considered as part of the examination process. This will also be published, separately, under the ‘Section 51 advice’ tab on the project page. Updates to the s51 advice log will be published as necessary throughout the pre-application stage under the ‘Section 51 advice’ tab on the project page on the Find a National Infrastructure Project website. See the Planning Inspectorate’s advice on how to submit an application for development consent for more information.